Hex Beam - Phase 2 Completed
Submitted by K9ZXO on Mon, 05/27/2019 - 5:08pm
Memorial day provided a perfect time to complete phase 2 of the SVRC Hex Beam Project. A large volunteer crew assembled on Monday morning, May 27, to help with the ongoing plan to erect a Rohn tower on the roof of the Red Cross building – home of the SVRC club station. Thirty donated concrete blocks were taken from the parking lot to the roof where they were installed on the tower base that had been constructed a week earlier. Then the single section of Rohn tower and rotor were installed on the base. Only one step remains; installing the Hex Beam on the tower.